All Project
Project

Startup and commissioning of 17 compressor units "Kirishineftegasorgsynthez"

Location — Leningrad oblast
Facility — Oil processing rotating and heat-exchanging equipment
Scope of works — Startup and commissioning of 17 compressor units
Customer — ООО "Kirishineftegasorgsyntez"
Year — 2012

De-conservation and technical condition inspection of compressor upon transportation and installation, auxiliary systems testing and adjustment, unloaded startup, gas loaded startup, 72-hour run test, commissioning.