Ingersoll Rand compressors start up for "Kaszink"

Location
Republic of Kazakhstan
Scope of works
Startup and commissioning
Customer
PAO "Cryogenmash"
End user
Ust-Kamenogorsk metallurgical works
Year
2015

The scope of works performed on Ingersoll Rand (Cameron) 3MSGEP-16/15 compressor:

Leveling of compressor frame on the concrete foundation

Grouting of the compressor frame

Compressor gearbox installation

Gearbox release

Pre-alignment of the electric motor 

Coolers (heat-exchangers) installation 

Ducts and IGV installation 

Grouting of the electric motor and heat exchangers (coolers) 

Oil and water pipes connection

Power and control cables, instrument air connection 

Oil in the lube-oil tank

Control system testing 

Oil system startup

Main electric motor testing 

Shaft installation and final alignment of the electric motor with compressor 

Compressor startup and tuning

72 hour run test, personnel training