The engineering company GazSurf carried out timely development in accordance with the Customer’s Terms of Reference, manufacture and supply of equipment for the associated petroleum gas dehydration unit at the Kokuy PPCS, as well as the MMR and commissioning complex. The scope of delivery included equipment for the units: an absorber with a built-in separator and a dry gas/lean TEG heat exchanger, TEG regeneration, thermal oxidation of the overhead product of the evaporation column, and auxiliary equipment.

06 мая 2021

Markovskiy field complex gas treating unit concept process design

Rostov region

Associated petroleum gas dehydration unit

Kazakhstan

The reconstruction of ethane recovery and nitrogen removal unit at Minnibaevskaya GPP

Tatarstan

Maintenance of CAMERON turbo compressor as part of ASU for KAZZINC