Commission of Oxygen plant GGMK Pokrovskiy rudnik

The GazSurf engineers continue commission of Oxygen plant of autoclave -hydrometallurgical complex of Pokrovskiy rudnik JSC. The oxygen plant consists of two ASU with summary capacity 23000 m3/h of gaseous oxygen.

Commissioning scope of works was caring out fettling works and start up compressors, blocks of cooling and air purification systems, as well test-run of turboexpanders of compressor assembly. Installed program facilities of automated management system of the oxygen station; implemented comprehensive debugging system. Provided complex of “hot” and “cold” tests of ASU blocks. At current stage perform ASU preparation for prestart landing of thermal insulator – perlitic sand.